Project Description
Tasu Construction partnered with BC Housing to design and construct a supportive housing complex on an undeveloped lot in Richmond, BC.
The three-storey modular building houses 40 residents in independent suites, including four accessible suites, additional common spaces, laundry facilities, storage, a commercial-grade kitchen, medical rooms, and outdoor amenities.
Modular units were manufactured offsite and transported to Richmond for assembly and installation to accelerate the project timeline and minimize costs. Tasu spearheaded all on-site planning and development aspects, from permitting and applications to mechanical, plumbing, electrical, and fire safety systems.
INDUSTRY: Rapid Response to Homelessness
CLIENT: BC Housing
LOCATION: Richmond, BC
COMPLETION: May 2022
CAPACITY: 40
TERM: 5 Years
DURATION: 180 Days
Project Scope
- Design, Engineering & Permitting
- Project Management
- Transportation & Logistics
- Modular Housing Installation
- Utilities & Support Systems